Celebrating a decade of Ben Houchen boondoggles: here’s the Top 20

A Ben’s Boondoggle is a boondoggle conjured up by Ben Houchen The post Celebrating a decade of Ben Houchen boondoggles: here’s the Top 20 appeared first on Bylines Network.

Celebrating a decade of Ben Houchen boondoggles: here’s the Top 20

On 18 November, Private Eye reported that Ben Houchen’s flagship project, the AI data centre at the former Redcar Steelworks, had been cancelled by Anthropic. The following day, Tees Valley Monitor asked whether Andy Burnham might attempt to rescue the data centre, as a vital piece of UK infrastructure. But seasoned Houchen-watchers will know that the Redcar data centre has all of the features of a Ben’s Boondoggle.

What is a Ben’s Boondoggle?

First of all, what’s a Boondoggle? The Cambridge Dictionary is here to help:

BOONDOGGLE | English meaning – Cambridge Dictionary

an unnecessary and expensive piece of work, especially one paid for by the public.

A Ben’s Boondoggle is a boondoggle conjured up by Ben Houchen. Some don’t get beyond the drawing board. The ones that do never live up to the initial promise. But one thing that they’ve got in common is that they waste public cash, sometimes quite a lot of it.

How do you spot a Ben’s Boondoggle?

The boondoggle usually arrives in the form of a press release about new jobs and investment. If the press release mentions something like 1,000 jobs and £1bn in investment, you’ve got yourself a Ben’s Boondoggle. There’ll usually be some extra imaginary construction and supply chain jobs thrown in. The icing on the cake will be a claim of 20,000 highly-paid, highly-skilled jobs coming soon to Teesworks/Teesside Freeport/Redcar, whatever. Sometimes Ben, or one of his Joint Venture cronies, will get ahead of themselves. Dubai-based scrap metal dealer Chris Musgrave once promised 45,000 Teesworks jobs.

Is anyone keeping track of these Ben’s Boondoggles?

I’m glad you asked. I’ve created a list of the Top 20 most egregious Ben’s Boondoggles that have appeared since Lord Houchen became Tees Valley Mayor almost a decade ago.

Ben’s Boondoggle #1 – The Redcar data centre

Back on 2 February this year, Ben Houchen attended a Northern Echo “IMPACT” event entitled “Teesside’s green revolution”. Spoiler alert: The “Teesside green revolution” doesn’t exist, but the Tees Valley Mayor was enthusing about data centres. I reported on the IMPACT event for North East Bylines. You can read my report here, in which I discussed, in detail, the impossibility of delivering a data centre at the scale promised by Ben Houchen. But this didn’t stop the relentless flow of empty promises. For example, on his BBC Tees monthly phone-in on 4 November 2026, Houchen ludicrously claimed that 500 data centre electrical engineers would be earning six-figure salaries. The Teesworks Joint Venture partners were aware by this date that the Redcar data centre project was in trouble, and there’s a good chance that Ben Houchen was aware too. But he didn’t break his stride when continuing to boost the ailing project.

Ben’s Boondoggle #2 – BP Blue and Green Hydrogen projects

This boondoggle is significant, because two BP hydrogen plants were meant to be built on the “Foundry”, in the same place as the short-lived data centre. While BP was trying to iron out the details of its projects, Teesworks Joint Venture Partners, Chris Musgrave and property mogul Martin Corney, were already talking to Google about building a data centre on the same piece of land. Within the space of a few months, BP cancelled HyGreen, and then H2Teesside, which were, respectively, the green and blue hydrogen projects. The Google data centre talks then came to nothing. Anthropic stepped in, but now it’s walked away too. Three investors have now pulled out of contracts for the same plot of land in Redcar.

Ben’s Boondoggle #3 – Net Zero Teesside

NZT’s carbon capture project is the flavour of the month Ben’s Boondoggle. But carbon capture is a complete waste of time, energy and money. When scientific reality catches up with the carbon capture hyperbole, NZT will become a “stranded asset”, which is an economist’s word for a Ben’s Boondoggle.

Ben’s Boondoggle #4 – Teesside Airport

At this stage the airport is £155mn in debt, including £27mn in unpaid loan interest. Neither of these will ever be repaid. The airport loses £10mn each year while flying 250,000 passengers. So, each return flight is subsidised via public funds to the tune of £80 per passenger. The Tees Valley Combined Authority (TVCA) recently awarded real estate consultants Jones Lang LaSalle a £30k contract to put a valuation on Teesside Airport. They could have waited until this article was published, and saved themselves £30k. Right now the valuation is minus £155mn. At a time of a climate emergency and a cost of living crisis, we shouldn’t accept this Ben’s Boondoggle for a minute longer. Here are the latest dire passenger numbers for the airport.

Teesside Airport passenger statistics
Teesside Airport passenger statistics

Ben’s Boondoggle #5 – the SeAH Factory

I reported on the parlous state of SeAH’s monopile factory on 2 June, then updated the figures on 8 November. You can read those reports here and here. The SeAH Factory still hasn’t made any products, and it’s been a Ben’s Boondoggle ever since that famous “Love Hearts” construction cosplay photo opportunity with Redcar MP Jacob Young on 14 February 2022.

Ben’s Boondoggle #6 – GE Wind Turbine Factory

The GE Wind Turbine Plant was supposed to be built next to South Bank Quay. Some classic Ben’s Boondoggle chat from Teesworks; 750 direct jobs and another 1,500 in the supply chain. The rush to prepare the site for GE led to the hasty demolition of the South Bank Coke Ovens, including the Dorman Long Tower. This, in turn, led to the Tees Bay crustacean die-off. GE cancelled the project a few months later, but it took Ben Houchen seven months to admit it. Houchen’s exaggeration of the scope of the development can be seen in Teesworks’ rendering, which showed factories stretching from the River Tees back to the A66, and taking in thousands of acres of land which are nothing to do with Teesworks.

Image from Teesworks

Ben’s Boondoggle #7 – South Bank Quay

Ironically, when Teesworks dredged the River Tees to build South Bank Quay, and the dredged silt was so toxic that it wasn’t allowed to dump it at sea, it was deposited on the site of one of the imaginary GE Factories in the above rendering. Teesworks Ltd bought the entire plot of land for South Bank Quay for £13.56 plus VAT, but the quay itself was financed by a £113mn loan to the South Tees Development Corporation (STDC) by the UK Investment Bank. The STDC transferred ownership of the quay to Teesworks Ltd, a move criticised in the Tees Valley Review Report because there was no written authority to do so. Then, in 2023, Teesworks handed the operation of the quay to Steel River Quay Ltd, a company 100% owned by Chris Musgrave and Martin Corney. South Bank Quay is up against stiff competition for offshore energy work, not only against other facilities on the River Tees, but also elsewhere in the North East of England and, indeed, the entire UK. Think of South Bank Quay as a dormant Ben’s Boondoggle.

Ben’s Boondoggle #8 – Sustainable Aviation Fuel (SAF)

SAF, just like carbon capture, is an elaborate con by the fossil fuel lobby. Unsurprisingly, there are at least six Teesside SAF Ben’s Boondoggles. I’ve bundled them together for the sake of brevity, but you can search these links if you are interested. Lighthouse Green Fuels, Lanzajet, Willis, Abundia, Arcadia, Skyfuel. Some of these projects date back almost two decades. Two things that they’ve got in common are (1) The ability to source UK government “research” grants, and (2) The inability to make SAF. Because none of them ever have.

Ben’s Boondoggle #9 – All of the hydrogen projects

We’ve already looked at BP’s two failed hydrogen projects, but they’re not the only Ben’s Boondoggles from the world of hydrogen hype. There’s Protium, which plans to make its green hydrogen via electricity from the national grid, but will certify it as “green” using an accounting trick. But Protium’s multicoloured hydrogen was first promised five and a half years ago, and it still hasn’t materialised. So maybe that clever accountancy won’t ever be needed. Don’t confuse Protium with EDF’s Tees Green Hydrogen, which was also announced in March 2021, and also has never left the drawing board. Then there’s the H2NorthEast (not to be confused with BP’s H2Teesside). You guessed it: That was also launched in 2021, and has been gathering dust ever since. H2NorthEast would be a blue hydrogen project, for fans of the hydrogen spectrum.

Ben’s Boondoggle #10 – Circular Fuels

Circular Fuels Ltd has got plans to make “renewable dimethyl ether” at a factory at Dorman Point in Grangetown. But you’re ahead of me, this one’s from 2021 too. A lot of Ben’s Boondoggles are celebrating their fifth birthday this year. But the market for renewable dimethyl ether must have collapsed since 2021, and nothing further has been heard from this Ben’s Boondoggle.

Ben’s Boondoggle #11 – Tees Valley Lithium

Another project that was announced in March 2021. No wonder Ben Houchen won the May 2021 Tees Valley Mayoral Election by a landslide – he promised half a dozen Ben’s Boondoggles in the two months leading up to it. Tees Valley Lithium has put out the occasional press release then, to create the illusion of activity, but it’s more than likely that it will remain a Ben’s Boondoggle.

Ben’s Boondoggle #12 – Tees Valley Graphite

Okay, you’ve guessed the year by now. Tees Valley Graphite will be brought to you by the same company behind Tees Valley Lithium. This “world class facility” will produce 20,000 tonnes of “active anode material” for sale into mobile phone batteries using graphite mined in Mozambique. Five years on from that blurb, we can safely file Tees Valley Graphite under “B” for Ben’s Boondoggle.

Ben’s Boondoggle #13 – Autonomous ‘tram-like service’

Plans for tram systems for all five main towns in the Tees Valley, Darlington, Hartlepool, Middlesbrough, Redcar and Stockton, were announced almost three years ago. The trams would be trackless (technically known as “buses”) and would operate a “hop on, hop off” service along unspecified routes. In February 2025, Ben Houchen’s TVCA boasted that the first trackless trams would be running through the Tees Valley by the end of 2025. It’s almost the end of 2026, and there’s still no sign of the trackless trams.

Ben’s Boondoggle #14 – All of the other January 2024 election promises

Teesside Park railway stationDirect rail services between Darlington and HartlepoolSouth Bank railway station transport hub
New Platform 3 at Middlesbrough StationGauge clearance work on Eaglescliffe to Northallerton railway lineBringing the Transporter Bridge back into action
Delivering a British Steel lorry parkTeesside Airport railway stationBus Station improvements for Middlesbrough
Options for an A19 Tees CrossingEastern Tees Crossing feasibility studyElectrification of the rail route between Northallerton and Saltburn
Removing West Dyke Road Level Crossing in RedcarEast Cleveland railway lineMiddlesbrough to Nunthorpe rail enhancement

Ben’s Boondoggle #15 – Aurrigo Autoshuttle and the Auto-Dolly Tug

No, it’s not a fading 1970s prog rock act, but a method of autonomously moving passengers and luggage around Teesside Airport. If they ever work. The Autoshuttle and the Auto-Dolly Tug were meant to start operating in January 2026, but the launch has just been postponed to “early 2027”. This is a photo of an Aurrigo Autoshuttle. Don’t worry, it hasn’t crashed, it’s meant to look like this.

Image from Aurrigo International plc

Ben’s Boondoggle #16 – Tees Flex

A taxi service without the convenience of a taxi, this Ben’s Boondoggle was unveiled in February 2020. In fact 60% of Tees Flex journeys transported only one passenger. In just over six years, Ben Houchen threw away £7.2mn on his pet boondoggle. In a rare show of strength from the local authority leaders within the TVCA Cabinet, they decided to axe Tees Flex in March 2026.

Ben’s Boondoggle #17 – Electric Arc Furnace

Okay, then, seeing as you are asking: Ben Houchen, why did you promise Teessiders, on numerous occasions between 2020 and 2025, and especially this one in 2023, that you would bring an Electric Arc Furnace to Teesside, when you knew that there was no way you could ever fulfil this promise?

Ben’s Boondoggle #18 – North Tees Hospital

As part of his re-election campaign, in January 2024, Ben Houchen promised Teessiders that he would build a new General Hospital at North Tees in Stockton. Since then, we’ve had almost three years of excuses from Houchen about his failure to deliver a promise that he could never have delivered on.

Ben’s Boondoggle #19 – E-Scooters

From TVCA

“E-Scooters to be made road-legal” said Ben Houchen in June 2020. Huge if true. It wasn’t. Houchen’s TVCA began the UK’s first trial of E-Scooters the following month. Thankfully the UK Government has never agreed with Houchen’s wise words from six years ago, and E-Scooters still aren’t road-legal. But that hasn’t stopped at least 66 people being killed by them since 2019. This Ben’s Boondoggle quietly went to Scooter Heaven in 2023 without any press announcements.

Boondoggle #20 – The Gresham Project

Ben Houchen launched a rebrand of this ailing central Middlesbrough regeneration project in May 2025. This was several reboots after it had been created by Middlesbrough Mayor Ray Mallon in 2002. By 2013, Mallon had left the area in ruins and the Gresham scheme was paused. The moral of the story should have been to stop electing self-promoting narcissists, but we never learn. In 2025, Ben Houchen chose to relaunch Middlesbrough’s flagship regeneration project 70 miles away in Leeds for some reason. The cost of Gresham had suddenly escalated from £120mn to £200mn, and the project was to be rebranded “Crown Square” to avoid association with the numerous Gresham failures. The scheme was finally good to go. Two months later, the developers pulled the plug on the whole thing. Ben’s Boondoggles don’t get any better than this.

Crown pub, photo by Ray Casey
Crown pub, photo by Ray Casey

Boondoggle #20 – The Epilogue: The dog ate Ben Houchen’s homework. Again

On 23 November, over a year after this Ben’s Boondoggle collapsed, Lord Houchen told Daniel Hodgson of the Local Democracy Service that Gresham will now be “less ambitious” than anticipated. Houchen continued “because of the major macro problems that have appeared over the past couple of years, it is going to be a different scheme”. Who could have known? I’ll leave the final word to the politician who said, two years ago “for far too long, Gresham has been a byword for the failure of those in charge to get a grip”. That politician was, of course, Ben Houchen.

Thanks to James Waterson for providing additional research for this article.