São Tomé Lembá Bridge Runs 1 Year Late Over Soil Tests
São Tomé's World Bank-funded Lembá bridge is a year late after drilling found 13 metres of mud, and the roads chief now promises completion in 2027. The post São Tomé Lembá Bridge Runs 1 Year Late Over Soil Tests appeared first on The Rio Times.
São Tomé's World Bank-funded Lembá bridge is a year late after drilling found 13 metres of mud, and the roads chief now promises completion in 2027.