Knysna sports field delays spark funding and payment issues
Knysna sports field delays spark funding and payment issues
For nearly six months, the Knysna municipality continued paying contractor Mosa Lesareng Trading and Projects, which was awarded an R8.7m tender, for the Bongani phase 2 sports field upgrade, despite no work being completed on site.